The critical path for the network activities shown below is __ with duration ___
Activity |
Duration |
Immediate Predecessors |
A |
2 |
– |
B |
4 |
– |
C |
1 |
A,B |
D |
6 |
A,B |
E |
3 |
B,C,D |
Below is a diagram of the project network:
Project completion is via A-C-E and B-D-E
Duration on path A-C-E = 2 + 1 + 3 = 6
Duration along B-D-E = 4 +6 + 3 = 13
Because B-D-E is longer than time,
The path to network activities must be along B-D-E, with duration 13.